how do I job charge and item from stock. We buy material to place in stock and I want to job charge it as it goes to a job.
Lots of ways, My favorite work around:
1. create a fiticious job called "Stock"
2. when you buy stock materials (not inventory tracking) using non-inventory items or other charge items, assign the Stock job.
3. When you need to shift the cost from Stock to Actual job use a -0- check method.
4. On a Write Check form, assign a fiticious bank account at the top, called Allocations.
5. On the Write Check form use the items tab, row one enter a negative amount and assign the Stock Job. on line two enter a positive amount and the actual job.
You have to know what your cost for materials are since you are not truly managing inventory.
Laura Madeira
Author of "QuickBooks 2009 Solutions Guide for Business Owners and Accountants"
National Trainer for Intuit Accountant Trainer/Writer Network
Soon to be released: QuickBooks Essentials - 10 hours of self-paced learning QuickBooks on DVD.
Visit my profile at:
https://community.intuit.com/m...
Please mark this answer as solved or post additional questions. Thanks so much!!!